More than 35 years' experience in all aspects of power stations worldwide, from original manufacture through to statutory inspections. Specialising in material selection, risk based inspection regimes, and flaw detection. Responsible for run, repair, replace decisions on major high temperature, high pressure plant. Outage planning and management.

Areas of Expertise

  • Welding engineering.
  • Risk-based inspection program development and management.
  • Outage planning and management.
  • Quality assurance and manufacturing.
  • Plant integrity and life assessment.
  • Pressure equipment inspections to statutory requirements.
  • Root cause failure analysis and mitigation.

Relevant Project Experience

  • PROJECT | Unit 1 Major Outage, Millmerran Power Station
    Client: Millmerran Operating Company
    Role: Outage technical manager
    Key achievements:
    Managed technical aspects of a major power station outage including on-site NDT and inspection.
    Responsible for liaising with and advising power station staff on run/repair/replace issues.
    Development of welding repair procedures for various plant.
    Signing off on plant inspections to ensure compliance with the statutory requirements.
  • PROJECT | Unit 1 Refurbishment, Calaca Power Station, Philippines
    Client: DM Consunji Inc
    Role: Principal materials engineer and independent technical advisor
    Key achievements:
    On-site assistance during major refurbishment.
    Provision of materials advice on high energy piping.
    Development of risk-based inspection program for high temperature and high pressure plant.
    Management of on-site NDT and inspection.
  • PROJECT | Weld repair of high energy piping, Quezon Power Station, Philippines
    Client: Pearl Energy Philippines Operating, Inc.
    Role: Principal materials engineer and independent technical advisor
    Key achievements:
    Desktop-based provision of a weld repair procedure for a major failure on the main steam line.
    Management of subsequent laboratory-based failure investigation.
    Development of risk-based inspection program for all high energy pipework in the station.

Qualifications

  • MSc Engineering (Welding)
  • Senior AICIP Inspector 0076
  • Registered Professional Engineer,
  • Queensland (RPEQ) 10072

Professional Associations and Memberships

  • Member of WTIA
  • Chartered Material Professional with Materials Australia

News and
Events

Read All news

Defect Tolerance Assessment (DTA) and Life Assessment of Turbine Rotor

Feb 02 2017
Defect Tolerance Assessment (DTA) I ( Ninh Nguygen) have had and two articles presented at the WTIA and IEAust conferences and publishe...

Effects of Mercury on an Aluminium Heat Exchanger in a Natural Gas Plant

Jan 24 2017
Heat Exchange - Major Failure At 2:43 am on the 1st of January 2004 an explosion and fire was caused by the failure of a cold box manifold.&...

Improving Efficiency in Thermal Power Plants

Jan 18 2017
Plant Performance HRL Technology Group's plant performance team has extensive experience in thermal power plant performance testing an...